Review of the permitting process for renewable power projects by international IPPs in Ethiopia

Navigating regulatory requirements for IPP engagement in Ethiopia's power sector

ERG reviewed the permitting process for IPP engagement in the power sector in Ethiopia for a company shortlisted for the Metahara 100MW solar plant tender. All relevant federal and regional level laws and procedures applicable in Ethiopia for IPP engagement were reviewed. A process map for meeting the regulatory requirements including time and finance required was prepared.

Client

MWH Consulting, Italy

Year

2016

Duration

4 months

Location

Ethiopia

Objectives

  • Review permitting process for IPP power projects
  • Analyze federal and regional laws for IPP engagement
  • Map regulatory requirements and procedures
  • Assess time and financial requirements for compliance

Outcomes

  • Comprehensive review of IPP regulatory framework
  • Process map for regulatory compliance
  • Time and cost analysis for permitting
  • Strategic guidance for Metahara 100MW solar plant tender